England · Statutory guidance
Conservation of fuel and power: Approved Document L, Volume 1 — Dwellings
Building regulation guidance on energy efficiency and the conservation of fuel and power.
- Edition
- 2021 edition incorporating 2023 amendments · Volume 1; later editions and transitions on source page
- Search coverage
- 104 of 104 PDF pages · 3 OCR pages
Energy & sustainability
Open original PDF at page 63 Source wording and page order preserved. Drawings and table layouts remain available in the original PDF.
O N L I N E V E R S I O N
R44, R44ZA, L1(b), L2(b)
Regulations 44 and 44ZA and requirements
L1(b)(iii) and L2(b): Commissioning
This section deals with the requirements of regulations 44 and 44ZA and Part L1(b)(iii) and L2(b) of
Schedule 1 to the Building Regulations 2010.
Regulation
Commissioning
44. (1) T his regulation applies to building work in relation to which paragraph F1(2) of Schedule 1 imposes
a requirement, but does not apply to the provision or extension of any fixed system for mechanical
ventilation or any associated controls where testing and adjustment is not possible.
(2) T his regulation applies to building work in relation to which paragraph L1(b) of Schedule 1 imposes
a requirement, but does not apply to the provision or extension of any fixed building service where
testing and adjustment is not possible or would not affect the energy efficiency of that fixed building
service.
(3) W here this regulation applies the person carrying out the work shall, for the purpose of ensuring
compliance with paragraph F1(2) or L1(b) of Schedule 1, give to the local authority a notice confirming
that the fixed building services have been commissioned in accordance with a procedure approved by
the Secretary of State.
(4) T he notice shall be given to the local authority—
(a) not later than the date on which the notice required by regulation 16(4) is required to be given; or
(b) where that regulation does not apply, not more than 30 days after completion of the work.
Commissioning in respect of a system for on-site electricity generation
44ZA. (1) T his regulation applies to building work in respect of a building in relation to which paragraph L2 of
Schedule 1 imposes a requirement, but does not apply to the provision or extension of any system for
on-site electricity generation where testing and adjustment is not possible.
(2) W here this regulation applies the person carrying out the work must, for the purpose of ensuring
compliance with paragraph L2 of Schedule 1, give to the local authority a notice confirming that the
system for on-site electricity generation has been commissioned.
(3) The notice must be given to the local authority—
(a) not later than the date on which the notice required by regulation 16(4) is required to be given; or
(b) where that regulation does not apply, not more than 30 days after completion of the work.
Building Regulations 2010 Approved Document L Volume 1, 2021 edition 53
O N L I N E V E R S I O N
Edition and local adoption determine which requirements apply. Use the publisher’s document for the complete clauses, diagrams and amendments.