England · Statutory guidance
Conservation of fuel and power: Approved Document L, Volume 2 — Buildings other than dwellings
Energy performance guidance for non-domestic buildings, covering fabric, services, controls and commissioning.
- Edition
- 2021 edition incorporating 2023 amendments · Volume 2; later editions and transitions on source page
- Search coverage
- 116 of 116 PDF pages · 2 OCR pages
Energy & sustainability
Open original PDF at page 71 Source wording and page order preserved. Drawings and table layouts remain available in the original PDF.
R44O, NRL I4N4E ZV EAR S,I OLN1(b), L2(b)
Section 8: Commissioning
8.1 Fixed building services must be commissioned to ensure that they use no more fuel and power than
is reasonable in the circumstances. On-site electricity generation systems must be commissioned
to ensure that they produce as much electricity as is reasonable in the circumstances. The
commissioning process should involve testing and adjusting the fixed building services and on-site
electricity generation as necessary and in accordance with the manufacturer’s instructions.
8.2 Fixed building services should be commissioned with the aim of optimising their in-use
performance, with reference to Section 5 and Section 6 of this approved document, which provide
further guidance on minimum efficiencies, controls and other relevant standards.
8.3 For large or complex projects, a commissioning manager should be appointed. In all other cases,
the appointment of a commissioning manager should be considered on a case-by-case basis. The
competence of the commissioning manager should meet the list of knowledge and skills set out in
CIBSE’s Commissioning Code M.
8.4 When installing a fixed building service, or on-site electricity generation that is subject to the
energy efficiency requirements, a commissioning plan should be prepared that identifies all of the
following.
a. The systems to test.
b. The tests to complete.
c. Schedule of commissioning.
d. Roles and responsibilities.
e. Documentation requirements.
The building control body should be given all of the following.
a. The commissioning plan.
b. The design-stage target primary energy rate and building primary energy rate calculation.
c. The design-stage target emission rate and building emission rate calculation.
The building control body can then check that commissioning is being done as the work proceeds.
8.5 If the only controls for a fixed building service or on-site electricity generation are ‘on’ and ‘off’
switches, this particular service does not need to be commissioned.
8.6 Any commissioning should be carried out in accordance with all of the following procedures.
a. CIBSE’s Commissioning Code M.
b. Any of the following.
i. The specific CIBSE Commissioning Codes relevant to each service being commissioned.
ii. The specific BSRIA Commissioning Guides relevant to each service being commissioned.
iii. A combination of (i) and (ii).
c. The procedures for air leakage testing of ductwork given in paragraphs 8.10 to 8.13.
61
Building Regulations 2010 Approved Document L Volume 2, 2021 edition
O N L I N E V E R S I O N