England · Statutory guidance
Conservation of fuel and power: Approved Document L, Volume 2 — Buildings other than dwellings
Energy performance guidance for non-domestic buildings, covering fabric, services, controls and commissioning.
- Edition
- 2021 edition incorporating 2023 amendments · Volume 2; later editions and transitions on source page
- Search coverage
- 116 of 116 PDF pages · 2 OCR pages
Energy & sustainability
Open original PDF at page 87 Source wording and page order preserved. Drawings and table layouts remain available in the original PDF.
RO6N L, I RN E2 V2E R, SRI O2N3(1), L1(a)
Section 11: Work to fabric elements in existing
buildings
General
11.1 This section provides guidance for work to fabric elements in existing buildings, including all of the
following types of work.
a. Renovating an existing thermal element in an existing building – follow paragraphs 11.2 to 11.4.
b. Making a material change of use to a building – follow paragraphs 11.5 to 11.8.
c. Making a change to a building that constitutes a change to energy status – follow paragraphs 11.6
to 11.8.
NOTE: For new and replacement elements in existing buildings, the guidance in Section 10 should
be followed.
Renovating thermal elements
11.2 Renovation of a thermal element means one of the following.
a. Providing a new layer through cladding or rendering the external surface of the thermal element.
b. Providing a new layer through dry-lining the internal surface of a thermal element.
c. Replacing an existing layer through stripping down the element to expose basic structural
components (e.g. bricks, blocks, rafters, joists, frame) and then rebuilding.
d. Replacing the waterproof membrane on a flat roof.
e. Providing cavity wall insulation.
11.3 If a thermal element is renovated and one of the following applies, then the whole of the thermal
element should be improved to achieve at least the U-value in Table 4.2 column (b).
a. More than 50% of the surface of the individual thermal element is renovated (see paragraph 11.4).
b. The work constitutes a major renovation. A major renovation is when more than 25% of the
surface area of the external building envelope is renovated.
11.4 When assessing the percentage area that will be renovated of an individual thermal element,
consider whether the element is being renovated from the outside or inside, following Diagram 11.1
and Diagram 11.2, respectively.
77
Building Regulations 2010 Approved Document L Volume 2, 2021 edition
O N L I N E V E R S I O N