England · Statutory guidance
Conservation of fuel and power: Approved Document L, Volume 1 — Dwellings
Building regulation guidance on energy efficiency and the conservation of fuel and power.
- Edition
- 2021 edition incorporating 2023 amendments · Volume 1; later editions and transitions on source page
- Search coverage
- 104 of 104 PDF pages · 3 OCR pages
Energy & sustainability
Open original PDF at page 66 Source wording and page order preserved. Drawings and table layouts remain available in the original PDF.
O N L I N E V E R S I O N
R44, R44ZA, L1(b), L2(b)
System specific guidance for commissioning
Hot water systems for space and domestic hot water heating
8.8 Before a new heating appliance is installed, all central heating and primary hot water circuits should
be thoroughly cleaned and flushed out. A suitable chemical inhibitor should be added to the
primary heating circuit to protect against scale and corrosion. In hard water areas, suitable measures
should be taken to treat the feed water to water heaters and the hot water circuit of combination
boilers to reduce limescale accumulation. Domestic central heating systems should be prepared and
commissioned to BS 7593.
NOTE: The Benchmark Commissioning Checklist can be used to show that commissioning has been
carried out satisfactorily for the heating and hot water system and its heat generation source.
Heat pump heating systems
8.9 Heat pumps and any dedicated ancillary products, e.g. integrated hot water cylinders, should be
commissioned in accordance with both the manufacturer’s instructions and the appropriate system
design parameters.
8.10 If using a ground source heat pump the commissioning procedure for the ground array should be
as follows.
a. Ground arrays – including header pipes and manifolds – should be flushed as one system to
remove all debris and purged to remove all air. Vertical, horizontal and slinky ground arrays in
particular should be flushed in both directions. During this process, the heat pump (along with
its accompanying pipework) should be isolated from the ground heat exchanger such that
damage to the internal heat exchanger inside the heat pump is avoided.
b. The heat pump – along with its accompanying pipework – should be flushed and purged as a
separate system while isolated from the ground array system.
c. Following the complete purging of micro air bubbles, a pressure test (in accordance with
BS EN 805, section 11.3.3.4) should be conducted on all closed-loop ground source heat pump
installations to prove the integrity of the systems. This test should be conducted on the entire
system, which typically comprises the heat pump, header pipes, manifold and all ground arrays.
d. Antifreeze and biocide should be added to ground heat exchangers as appropriate, in line with
manufacturer’s instructions.
8.11 Commissioning information provided to the dwelling owner should include details of the fluids
used and their comissioned concentrations.
Community heating systems
8.12 For district heat networks and community heating systems, both of the following should be done.
a. Systems should be commissioned to optimise the use of energy for pumping.
b. Flow rates in individual heat emitters should be balanced using either of the following.
i. Appropriate return temperatures.
ii. Calibrated control valves.
Underfloor heating
8.13 All installed equipment in underfloor heating systems should be commissioned in accordance with
BS EN 1264-4.
56 Approved Document L Volume 1, 2021 edition Building Regulations 2010
O N L I N E V E R S I O N
Edition and local adoption determine which requirements apply. Use the publisher’s document for the complete clauses, diagrams and amendments.