A1/2
Section 2E: Foundations of plain concrete
Conditions relating to the ground
Diagram 21 Elevation of stepped
2E1 There should not be: foundation
a. non-engineered fill (as described in BRE
See paras 2E2d and e
Digest 427) or wide variation in ground
conditions within the loaded area; nor
b. weaker or more compressible ground at
such a depth below the foundation as could
impair the stability of the structure.
Design provisions
2E2 The following design provisions relate to
foundations:
a. the foundations should be situated centrally
under the wall;
b. for foundations in chemically aggressive
soil conditions guidance in BS 8500-1 and
BRE Special Digest 1 should be followed.
In non-aggressive soils, concrete should
be composed of Portland cement to BS EN
197-1 and -2 and fine and coarse aggregate
conforming to BS EN 12620 and the mix
should comply with one of the following Diagram 22 Piers and chimneys
recommendations:
i. in proportion of 50kg of Portland cement See para 2E2f
to not more than 200kg (0.1m3) of fine
aggregate and 400kg (0.2m3) of coarse
aggregate; or
ii. grade ST2 or grade GEN I concrete to
BS 8500-2;
c. minimum thickness T of concrete foundation
should be 150mm or P, whichever is the
greater, where P is derived using Table 10
and Diagram 23. Trench fill foundations may
be used as an acceptable alternative to strip
foundations;
d. foundations stepped on elevation should
overlap by twice the height of the step, by Diagram 23 Foundation dimensions
the thickness of the foundation, or 300mm,
whichever is greater (see Diagram 21). See para 2E2c
For trench fill foundations the overlap should
be twice the height of the step or 1m,
whichever is greater;
e. steps in foundations should not be of greater
height than the thickness of the foundation
(see Diagram 21);
f. foundations for piers, buttresses and chimneys
should project as indicated in Diagram 22 and
the projection X should never be less than the
value of P where there is no local thickening
of the wall.
Minimum width of strip
foundations
2E3 The recommended minimum widths of
foundations given in Table 10 may be used.