England · Statutory guidance
Conservation of fuel and power: Approved Document L, Volume 2 — Buildings other than dwellings
Energy performance guidance for non-domestic buildings, covering fabric, services, controls and commissioning.
- Edition
- 2021 edition incorporating 2023 amendments · Volume 2; later editions and transitions on source page
- Search coverage
- 116 of 116 PDF pages · 2 OCR pages
Energy & sustainability
Open original PDF at page 67 Source wording and page order preserved. Drawings and table layouts remain available in the original PDF.
O N L I N E V E R S I O N R43
Section 7: Air permeability and pressure
testing
7.1 The minimum standard for air permeability of a new building is given in Table 4.1 of Section 4.
7.2 The building control body should be provided with evidence that test equipment has been
calibrated using a UKAS-accredited facility or by the original manufacturer within either of the
following periods.
a. The previous 12 months.
b. A period in accordance with manufacturer’s guidance.
Calibration should be carried out in accordance with CIBSE’s TM23. It is recommended that test
equipment is recalibrated at least every 24 months.
7.3 Building control bodies may accept a pressure test certificate as evidence that the building
complies with regulation 43 of the Building Regulations.
The building control body should be provided with evidence that the person who pressure-tested
the building meets both of the following.
a. Has received appropriate training.
b. Is registered to test the specific class of building.
7.4 Buildings that are not dwellings, including extensions that are being treated as new buildings to
comply with Part L, must be pressure tested except those types listed in paragraph 7.5.
7.5 The following buildings do not need to undergo pressure testing.
a. Buildings with less than 500m2 total useful floor area. In this case the developer may avoid a
pressure test, provided that the air permeability used to calculate the building primary energy
rate and building emission rate is taken as 15m3/(h·m2) at 50Pa.
b. A factory-made modular building that meets the following criteria:
i. the floor area is less than 500m2
ii. the building has a planned service life of more than two years, where the intended time of
use in a single location is less than two years
iii. no site assembly work is needed other than linking standard modules using standard link
details.
If the building as installed conforms to a standard configuration of modules and link details
for which the installer has pressure test data, this test data may be used to estimate the air
permeability. Test data must be from a minimum of five in-situ measurements of the same
module types and link details as used in the actual building. Air permeability should be in m3/
(h·m2) at 50Pa. When calculating the building primary energy rate and building emission rate for
a factory-made modular building as described above, the value that should be used for design air
permeability is the average air permeability test result at 50Pa plus 1.0m3/(h·m2).